United States · USD · ft / in
Multi-shape volume calculator

Concrete Yard Calculator

Add a slab, then a footing, then a few sonotubes — and get one combined yardage to order. Built for jobs where the same truck pours multiple shapes.

Volume Estimator · v3.2 · US
Items added 0 items
Add shapes above to build your total.

Combined Total

Order this much cu yd — with waste
  • Subtotal (raw)all items, no waste
  • Cubic feet / litres
  • Cubic metres
  • 80 lb bags~0.022 yd³ each
  • 60 lb bags~0.017 yd³ each
  • Weightdelivery planning
  • Costenter price below

From mixed shapes to one truck delivery.

Most real concrete jobs aren't a single rectangle. A typical house pour might include the slab, four corner footings, a couple of porch tubes, and a set of front steps — all from one truck. Adding shapes individually and ordering each separately wastes money on short-load fees and creates cold joints when the second pour arrives an hour late.

This calculator lets you stack shapes into one total. Each item is computed with the right formula, then summed, with waste applied at the end. The pipeline:

  1. Pick a shape — slab, footing, column, tube, stairs, or curb & gutter.
  2. Enter its dimensions and the quantity (one slab, four footings, eight tubes).
  3. Hit "Add to total." The item lands in the running list with its computed volume.
  4. Move to the next shape and repeat.
  5. The right panel sums every item, adds your waste factor, and gives the figure to call the ready-mix plant with.

The hero readout is in your country's primary unit — cubic yards in the US and Canada, cubic metres in the UK and Australia. Bag counts assume Quikrete-class pre-mix yields (~0.60 ft³ per 80 lb bag, ~0.45 ft³ per 60 lb bag). The weight figure assumes ~4,000 lb per cubic yard (~2,400 kg/m³) — useful for planning truck access, formwork loading, and trailer transport on DIY jobs.

How each shape is calculated.

Slab / Wall / Square Footing

V = L × W × T

The simplest case. Length × width × thickness, all in consistent units (feet or metres). Walls use the same formula — just substitute height for length and rotate the slab vertical.

Round Column / Tube / Sonotube

V = π × r² × H

Use radius (half the diameter), squared, times height. A 12-inch diameter sonotube 4 feet deep: π × 0.5² × 4 = 3.14 ft³ = 0.12 yd³. For ten of those, you need 1.2 yd³.

Strip Footing

V = L × W × D

Treated as a long thin rectangle — length × width × depth. For a continuous perimeter footing, length is the total run around the foundation. Width is typically 16–24 inches; depth is below frost line.

Stairs (cast in place)

V = ½ × tread × rise × width × n(n+1)

Each step is a stacked block. Step 1 sits on the ground, step 2 sits on a footprint of run × 2 tread depths, and so on. Sum the volume of every step plus the landing.

Curb & Gutter

V = (curb section area) × L

Compute the cross-sectional area of the curb profile (rectangular curb + sloped gutter pan) and multiply by total length. Most residential curbs are 6" wide × 18" tall; gutter pans add 12" × 4".

Hollow Tube / Pipe

V = π × (R² − r²) × H

Outer radius squared minus inner radius squared, times π, times height. Useful for pier collars, retaining wall caps, and cylindrical liners.

Once each shape is computed, the calculator converts internally to cubic metres for summing, then displays the total in your country's preferred unit. 27 cubic feet = 1 cubic yard. 1 cubic yard = 0.7646 cubic metres. Most ready-mix plants will round your order up to the next quarter unit (0.25 yd³ in the US, 0.25 m³ in the UK and Canada, 0.20 m³ in Australia).

Volume conversions and bag yields.

US volume reference
Convert fromToMultiplier
Cubic feetCubic yards÷ 27
Cubic feetCubic metres× 0.0283
Cubic yardsCubic metres× 0.7646
Cubic yardsSquare ft @ 4"× 81
Cubic yardsSquare ft @ 6"× 54
Cubic yards80 lb bags× 45
Cubic yards60 lb bags× 60
Cubic yards40 lb bags× 90
Cubic yardsPounds× 4,000

The "magic number is 81" rule. Contractors estimate 4-inch residential slabs by dividing square footage by 81. A 200 sq ft patio ÷ 81 = 2.47 yd³ — close enough to the 2.46 yd³ the formula gives you. For 6-inch slabs, divide by 54 instead.

UK volume reference
Convert fromToMultiplier
Cubic metresLitres× 1,000
Cubic metresCubic yards× 1.308
Cubic metresm² @ 100 mm× 10
Cubic metresm² @ 150 mm× 6.67
Cubic metres25 kg bags× 80
Cubic metres20 kg bags× 100
Cubic metresTonnes (concrete)× 2.4

Most UK builders' merchants stock 20 kg and 25 kg pre-mixed concrete bags. A 25 kg bag of Type S or general-purpose mix yields about 0.0125 m³ once water is added. Ready-mix lorries deliver in 0.25 m³ increments; mini-mix and barrow-run services suit jobs without 8-tonne truck access.

Australia volume reference
Convert fromToMultiplier
Cubic metresLitres× 1,000
Cubic metresCubic yards× 1.308
Cubic metresm² @ 100 mm× 10
Cubic metresm² @ 150 mm× 6.67
Cubic metres20 kg bags× 100
Cubic metres30 kg bags× 67
Cubic metresTonnes× 2.4

Australian batching plants deliver in 0.2 m³ increments via agitator trucks. Mini-mix trucks at 1.2 m³ capacity suit suburban access; Hi-Way or hand pumps cover sites where the agitator can't reach. Pre-mix bags from Boral, Hanson, and Cement Australia ship in 20 kg and 30 kg sizes.

Canada volume reference
Convert fromToMultiplier
Cubic feetCubic yards÷ 27
Cubic feetCubic metres× 0.0283
Cubic yardsCubic metres× 0.7646
Cubic yardsSquare ft @ 4"× 81
Cubic metresm² @ 100 mm× 10
Cubic yards30 kg bags× 51
Cubic yards25 kg bags× 61
Cubic yardsPounds× 4,000

Canadian construction uses both imperial and metric — material orders typically in cubic yards or cubic metres depending on supplier preference, with metric standard for engineered drawings (CSA codes). Sika, Quikrete Canada, and King Packaged Materials supply pre-mix bags in 25 kg and 30 kg sizes nationwide.

Why your order comes up short.

  • Mixing units. Putting feet in one input and inches in another is the most common error. Always convert thickness to feet (4 inches = 0.333 ft) before multiplying, or use a calculator that handles the conversion automatically.
  • Forgetting subgrade irregularity. If your excavated trench is half an inch deeper than nominal across 100 sq ft, that's an extra 0.15 yd³ you'll need. Bumping waste from 5% to 8% covers this in most cases.
  • Using triangle math for stairs. Stairs aren't a triangle — they're a stack of rectangular blocks. Step 2 sits on a footprint of (run × 2), step 3 on (run × 3), and so on. Triangle approximations under-count by 15–25%.
  • Ignoring wall taper. Basement and retaining walls often taper from a wider base to a narrower top. Average the top and bottom thicknesses before multiplying — never just use the wall's stated thickness at one end.
  • Confusing yards and feet. Ready-mix is sold by the cubic yard. Bag concrete coverage is rated in cubic feet. Mixing them up is how a job ordered as "3 yards" arrives as a quarter of what was needed.
The short-pour penalty. Ready-mix plants charge a small-load fee for partial loads — typically $50–$150 in the US, £60–£100 in the UK, A$130–A$180 in Australia, C$100–C$150 in Canada. Going back for a second delivery to make up for under-ordering costs more than just over-ordering by 5%. Order long, pour the extra into a footing or post hole if you have one ready.
Reviewed by Jordan Mireles, P.E. Licensed civil engineer · 14 years residential and light commercial concrete. Volume formulas verified against ACI 301 specifications, ASTM C94 ready-mix delivery standards, and standard estimating texts. Last reviewed May 2026.

Quick answers.

How do I calculate cubic yards of concrete?

Multiply length × width × thickness (all in feet) to get cubic feet, then divide by 27 to convert to cubic yards. For a 10 × 12 ft slab at 4 inches thick: 10 × 12 × (4/12) = 40 ft³, then 40 ÷ 27 = 1.48 cubic yards. Add 5–10% for waste.

How many cubic feet in a cubic yard?

27 cubic feet equal one cubic yard. A cubic yard is a 3-foot × 3-foot × 3-foot cube. Concrete is sold by the cubic yard in the US and Canada; the UK and Australia sell by the cubic metre, where 1 cubic yard equals 0.7646 cubic metres.

How much area does one cubic yard of concrete cover?

One cubic yard covers 81 sq ft at 4 inches thick, 54 sq ft at 6 inches thick, and 27 sq ft at 12 inches thick. The quick formula for a 4-inch slab is square footage ÷ 81 = cubic yards. For metric work, 1 m³ covers 10 m² at 100 mm or 6.67 m² at 150 mm.

How many 80 lb bags equal one cubic yard?

45 bags of 80 lb pre-mix, 60 bags of 60 lb pre-mix, or 90 bags of 40 lb pre-mix equal one cubic yard. Each 80 lb bag yields about 0.022 yd³ (0.6 ft³) of mixed concrete. For metric pre-mix: 100 × 20 kg bags or 80 × 25 kg bags per cubic metre.

What does a cubic yard of concrete weigh?

Roughly 4,000 pounds (1,815 kg) for typical structural concrete at 2,400 kg/m³ density. Lightweight aggregate mixes run 2,000–2,500 lb per yard; high-density radiation-shielding mixes can exceed 5,500 lb per yard. The weight matters for trailer transport, formwork loading, and small-load barrow runs on DIY jobs.

Should I round up or down on my order?

Always round up. Ready-mix plants deliver in quarter-unit increments (0.25 yd³ or 0.25 m³, 0.2 m³ in Australia) and a partial truck charges a short-load fee. Coming up short on a pour means a return trip, the short-load fee twice, and a cold joint in the finished slab where the two pours meet.