From dimensions to a clean order figure.
The volume math is the same everywhere: length × width × thickness. Get the three measurements into the same units, multiply, then add a waste factor. The calculator handles the unit conversions and the rounding step, and gives you bag counts at common sizes.
Cubic feet is the natural intermediate — 27 cubic feet equals one cubic yard. A 10 × 10 slab at 4 inches is 33.3 cubic feet, which works out to 1.23 cubic yards before waste. Add 8% and you order 1.5 yards because ready-mix plants bill in quarter-yard increments. Bag yields follow Quikrete and Sakrete specs: an 80 lb bag yields 0.60 ft³, a 60 lb bag yields 0.45 ft³.
Rebar estimates assume a #4 (½ inch) bar at 12 inches on centre each way — the residential default per ACI 332. If you've selected wire mesh instead, the bag of mesh handles a 100 ft² area at 6×6 W1.4 grade.
The UK works in cubic metres directly — length × width × thickness in metres gives you the order figure straight away. A 3 × 3 metre slab at 100 mm thick is 0.90 m³ before waste. Add 8% and you order 1.0 m³ because ready-mix lorries deliver in 0.25 m³ increments. Bag yields on UK pre-mixed concrete: a 20 kg bag gives about 0.010 m³, a 25 kg bag about 0.0125 m³.
Reinforcement estimates assume 12 mm bar at 200 mm centres each way — the typical residential slab to BS 8500. Wire mesh on a domestic slab is usually A142 (for paths) or A193 (for driveways) per BS 4483.
Australia works in cubic metres — length × width × thickness in metres gives the order figure directly. A 3 × 3 metre slab at 100 mm is 0.90 m³ before waste. Add 8% and order 1.0 m³; batching plants deliver in 0.2 m³ increments via agitator trucks. Bag yields from Boral, Hanson, and Cement Australia: a 20 kg bag gives about 0.010 m³, a 30 kg bag about 0.015 m³.
Reinforcement estimates use N12 deformed bar at 300 mm centres each way — typical for residential exposure class A1 or A2 to AS 3600. For waffle slabs and stiffened rafts under AS 2870, the bar schedule is engineered to site reactivity class.
Canada specifies in cubic metres — length × width × thickness in metres gives the order figure. A 3 × 3 metre slab at 100 mm thick is 0.90 m³ before waste. Add 8% and you order 1.0 m³; ready-mix is delivered in 0.25 m³ increments. Canadian bag yields (Sika, Quikrete Canada, King Packaged Materials): a 25 kg bag gives about 0.0125 m³, a 30 kg bag about 0.015 m³.
Reinforcement estimates use 15M bar at 300 mm centres each way — common for a residential slab or driveway under CSA A23.1. For unheated exterior slabs, exposure class C-2 or F-1 also drives the cover and air-entrainment requirements.
Waste factor. Five percent is the floor for clean, level, well-formed work. Eight percent is the residential default and what's preset on the calculator. Ten percent is for hand-dug footings, rough subgrade, or anything irregular. Running short by a tenth of a yard on a residential pour means a return trip, a small-load fee, and a cold joint in your slab — almost always more expensive than over-ordering.